When the Data Hall Itself Becomes the Project
A data center’s white space rarely sits empty by accident. In the Permian Basin, where oilfield operators, midstream companies and regional telecommunications providers rely on local network capacity, colocation space and edge facilities, white space projects typically surface for one of a few reasons: a lease is ending, a facility is being modernized with new rack density or cooling architecture, an operator is consolidating multiple halls into one, or a building is being repositioned for a different tenant entirely.
Midland–Odessa sits in the heart of the Permian Basin, one of the most active oil-and-gas producing regions in the country, and the metro functions as a hub for labor, logistics and support services throughout the surrounding area. That industrial base has supported network infrastructure ranging from carrier-neutral access points serving oilfield telemetry and SCADA systems to newer facilities positioned near the region’s power and gas resources. Whatever the trigger, the practical problem is the same: someone has to clear the raised floor, pull the racks, disassemble the containment, remove the overhead cable plant and hand back a data hall that’s actually usable for its next purpose.
If you have a project coming up, use the form below to tell our team about the facility, equipment and schedule.
That’s a different scope than decommissioning an entire facility or pulling specific mechanical and electrical equipment. White space decommissioning is about the room itself — the floor, the aisles, the infrastructure that made it a data center in the first place — and getting it to a condition where it can be renovated, re-tenanted or repurposed.
What’s Actually Inside a Data Hall When the Project Starts
Before a white space project can be scoped accurately, it helps to walk through what’s typically still standing when a hall goes dark. Server and network cabinets from manufacturers like APC/Schneider Electric, Chatsworth Products (CPI), Rittal, Panduit, Vertiv, Great Lakes Case & Cabinet, Eaton and Legrand make up the bulk of the visible footprint, often in rows of 50 to several hundred cabinets depending on the facility’s original design intent. Beneath the cabinets, many halls still run on raised access flooring from manufacturers such as Tate, ASM, Haworth or Kingspan — panel systems built around steel stringers and adjustable pedestals that create the underfloor plenum used for cooling airflow and cable distribution and are engineered for load capacity and airflow performance in mission-critical spaces.
Above the cabinets, overhead ladder rack, cable tray and fiber or copper cable plant from manufacturers like Chatsworth/CPI, Panduit, Legrand, Cablofil, Corning, CommScope and Belden typically run the full length of the hall, often layered from multiple technology refreshes over the facility’s life. Hot-aisle and cold-aisle containment — doors, roof panels, end caps and vertical partitions from providers such as APC/Schneider, Vertiv, Chatsworth, Subzero Engineering or Tate — usually remains in place as well, since containment is rarely removed until the racks it surrounds come out. Power distribution units, remote power panels and overhead or underfloor busway from Vertiv/Liebert, PDI, Eaton, APC/Schneider, Starline or Square D round out the electrical infrastructure that has to be de-energized, disconnected and removed as part of the scope. Depending on the facility, CRAC or CRAH units serving the white space and fire-suppression components tied to the hall’s detection and clean-agent systems may also fall within the project, particularly when the entire room — not just the rack rows — is being cleared for reuse.
Scoping the Project Before Anyone Touches a Rack
A white space decommissioning project starts with a walkthrough and an honest inventory, not a demolition crew. Our team typically works from as-built drawings when they’re available, but in facilities that have gone through several equipment refreshes, the drawings rarely match what’s actually in the room anymore. That means physically counting cabinets, documenting containment configurations, tracing cable pathways and identifying which power circuits are still live versus already abandoned. This step matters because the sequencing of a white space project — what gets de-energized first, what gets physically removed first, and what has to wait for utility or landlord coordination — depends entirely on an accurate picture of the room.
Square footage and rack count drive most of the planning decisions that follow. A 2,500 SF hall with 50 cabinets is a different project than an 80,000 SF hall with 900 or more cabinets, not just in labor hours but in loadout logistics, disposal volume and the number of work shifts required to hit a turnover deadline. Facility operators in the Midland-Odessa market often work against firm dates tied to lease expirations or landlord turnover requirements, and those dates need to drive the project schedule from day one rather than becoming a surprise near the end.

Shutdown, Disconnection and De-Energizing the Hall
Before any cabinet or piece of containment comes out, the electrical infrastructure feeding the white space has to be properly de-energized and disconnected. PDUs, RPPs and busway systems from manufacturers like Starline, Square D, Eaton and Vertiv/Liebert typically feed dozens or hundreds of individual circuits by the time a hall reaches end of life, and each one needs to be traced, isolated and confirmed dead before removal work begins. This is coordinated with the facility’s electrical contractor or engineer of record, particularly in halls that remain partially energized because other tenants or systems in the building are still operating.
Fire-suppression components tied to the white space — detection heads, clean-agent piping, control panels dedicated to the hall — are handled with the same care, since these systems are often integrated with building-wide life-safety systems that need to remain functional even after the data hall itself goes dark. Getting this sequencing wrong doesn’t just create safety exposure; it can also delay the entire project if a facility’s engineer has to stop work to re-verify isolation before removal can proceed.
Removing Racks, Containment and the Overhead Infrastructure
Once the hall is de-energized, the physical removal sequence generally moves from the top of the room down. Overhead cable tray, ladder rack and abandoned fiber or copper runs come out first in most halls, since this infrastructure often has to be cleared before containment roof panels and vertical barriers can be safely removed. Hot-aisle and cold-aisle containment systems are then disassembled — doors, end caps, roof structures and any ceiling-mounted framing — followed by the server and network cabinets themselves.
Cabinet removal sounds straightforward until you’re standing in a hall with several hundred racks bolted to a raised floor, many of them still containing cabling, blanking panels, PDUs and mounting hardware that has to be documented for disposition before the cabinet frame comes out. Heavier or fully populated cabinets may require mechanical assistance to move safely across the raised floor without damaging panels or the underlying pedestal grid. Raised access floor panels are typically removed last in the sequence, once the room above them is clear, since the underfloor plenum often still contains cable drops, grounding infrastructure and sometimes cooling ductwork that needs to be identified before the floor system itself is dismantled.
Working Around Active Systems and Operating Neighbors
Very few white space projects happen in a fully isolated, powered-down building. More commonly, the hall being cleared sits inside a facility where other tenants, other server rooms or other business operations continue running throughout the project. That reality shapes almost every decision on site — work hours may be restricted to avoid vibration or dust near occupied space, material staging has to account for shared loading docks and freight elevators, and noise-generating work like floor panel removal or structural cutting often gets scheduled around the building’s other occupants.
In multi-tenant colocation environments, this coordination becomes even more layered, since access to the white space itself may be restricted by security protocols, badge access schedules or landlord escort requirements that affect how quickly crews can move material in and out. A realistic project schedule accounts for these constraints from the planning stage rather than treating them as obstacles discovered mid-project.

Asset Recovery: What’s Worth Recovering Before It’s Scrapped
Not everything coming out of a data hall belongs in a scrap bin. Server and network cabinets in good condition, particularly from established manufacturers, may retain resale or reuse value depending on age, configuration and completeness. Raised floor panels and pedestal systems, containment doors and panels, and cable management hardware can sometimes be reused in other facilities or sold into the secondary market rather than landfilled. PDUs, RPPs and busway components — especially higher-capacity units from manufacturers like Starline, Eaton or Vertiv/Liebert — may also have recoverable value depending on condition and current demand.
The economics vary project to project. A hall with newer, well-maintained cabinets and containment in good physical condition presents a very different asset-recovery picture than one with older equipment that’s been through multiple refresh cycles. Copper cabling, structural steel from cable tray and containment framing, and electrical components pulled during disconnection all factor into the overall recycling and salvage plan for the project. Where equipment retains functional value, resale or reuse can offset a portion of the removal cost; where it doesn’t, responsible recycling keeps usable commodity value in copper, aluminum and steel out of a landfill. We evaluate each category of material on its own merits rather than treating an entire hall as either a salvage opportunity or a scrap job.
What to Gather Before Requesting a Quote
A useful starting point for scoping a Midland-Odessa white space project includes the hall’s approximate square footage, current rack count, and whether the space is fully de-energized or still carrying live circuits. Photos of the cabinet rows, containment system, raised floor condition and any overhead cable plant help our team understand scope before a site visit, along with any hard turnover date tied to a lease expiration or landlord deadline.
Serving the Permian Basin and Surrounding Markets
Beyond Midland and Odessa, our team provides white space decommissioning services throughout the broader Permian Basin, including Big Spring, Andrews, Monahans, Pecos and San Angelo. Facilities in these communities often share the same driver behind Midland-Odessa projects — network and colocation space built to support oilfield operations that eventually needs to be cleared for a new tenant or a different technology footprint.
Tell Us About Your Data Hall
If you’re planning a white space decommissioning project in Midland, Odessa or elsewhere in the Permian Basin, use the form below to tell our team about the facility — square footage, rack count, containment type, power status and target turnover date.