If your Fresno facility is decommissioning a server room, retiring a colocation suite, or replacing aging precision cooling infrastructure, the computer room air conditioning (CRAC) or computer room air handler (CRAH) units on your floor plan are some of the most physically demanding equipment to remove. These units are heavy, tied into refrigerant or chilled-water piping, wired into dedicated electrical circuits, and frequently installed in locations that were never designed with removal in mind — raised-floor data halls, mezzanine mechanical rooms, or tight equipment corridors behind rack rows.
USA Decom provides precision cooling removal services to facility managers, IT directors, mechanical contractors and property owners throughout Fresno and California’s Central Valley in connection with data center closures, equipment upgrades, tenant turnovers and facility consolidations. Below, we’ve organized this page around the questions Fresno-area facility managers most often ask before bringing in a contractor for this type of work.
What Counts as a CRAC or CRAH Unit, and Why Does the Difference Matter for Removal?
A CRAC unit conditions air using a direct-expansion (DX) refrigeration circuit, typically tied to an outdoor condenser or a chilled-water coil loop. A CRAH unit, by contrast, relies entirely on chilled water supplied from a central plant and has no refrigerant circuit of its own. The distinction matters for a removal project because it determines what has to happen before the unit can be disconnected:
- DX CRAC units require refrigerant recovery by a certified technician before any refrigerant lines are cut or the compressor section is opened for removal.
- Chilled-water CRAH units require the chilled-water supply and return piping to be isolated and drained rather than refrigerant recovery, though condensate and glycol lines still need to be handled properly.
- Air-cooled versus water/glycol-cooled DX systems each have different outdoor or remote condenser connections that also need to be traced and disconnected as part of the same scope.
Fresno data halls and server rooms can include both configurations, and older facilities sometimes have a mix — legacy DX perimeter units alongside newer chilled-water or in-row equipment added during a capacity upgrade. Identifying what’s actually installed, rather than relying on floor plans or nameplate assumptions, is one of the first things our team confirms during scope development.
Which Manufacturers and Models Are We Typically Removing?
Precision cooling equipment in Fresno server rooms and data centers tends to fall into a handful of well-established product families. Knowing which one you have helps us plan disconnection sequencing, rigging approach and equipment weight before crews arrive on site.
If you have a project coming up, use the form below to tell our team about the facility, equipment and schedule.
- Vertiv (Liebert) — Perimeter units such as the DS, DSE, CW and PDX/PCW families are common in raised-floor data halls, and the Liebert CRV in-row unit is often found integrated directly within rack rows in higher-density environments. Older sites may still be running legacy Liebert Challenger or Deluxe-series units.
- STULZ — CyberAir DX and CyberAir CW units are widely deployed in colocation and enterprise data centers, and CyberAir 3 units with free-cooling configurations show up in facilities that have adopted economizer-based cooling strategies. CyberRow and CyberOne in-row units also appear in higher-density rack configurations.
- Schneider Electric / APC / Uniflair — InRow RC and InRow RD units, along with legacy Uniflair and NetworkAIR perimeter models, are common in mid-size server rooms and network closets across the Central Valley.
- Data Aire — a familiar name in Western U.S. precision cooling installations, particularly in telecom and smaller enterprise data rooms.
Units in this category commonly range from roughly 5-ton wall-mounted or in-row systems up to 20-, 30- and 40-ton-plus perimeter units serving larger data halls. Larger units generally mean heavier cabinets, larger piping and ductwork connections, and more coordination around rigging paths and floor loading.

Why Fresno Facilities Are Retiring Precision Cooling Equipment
Fresno sits near the geographic center of California, and its position along the Highway 99 corridor has helped the region support logistics, food processing, agricultural technology and regional network infrastructure operations. As distribution operators and telecom providers have established a presence in the Central Valley, some facilities added server rooms, network operations spaces and small colocation footprints to support local operations. That equipment can reach a point where components are harder to source, certain refrigerants face phase-out restrictions, or consolidation into larger regional or cloud-based infrastructure changes what a given site actually needs on premises.
We also see CRAC and CRAH removal driven by more immediate project triggers:
- A tenant vacating a leased office or industrial building with a legacy server room that has to be cleared before turnover.
- A facility upgrading to newer in-row or higher-efficiency cooling and needing the old perimeter units removed to make room.
- A company consolidating multiple smaller data closets into a single upgraded space.
- A property being repositioned for a new use where the mechanical infrastructure from a prior tenant no longer applies.
Whatever the driver, the physical removal requirements are similar: safe disconnection, proper handling of refrigerant or chilled water, rigging the unit out of a constrained space, and disposition of the equipment once it’s out.
What Does the Refrigerant Recovery Requirement Actually Involve?
For any DX CRAC unit, refrigerant recovery is a required step before disposal or scrapping. Federal regulations governing stationary refrigeration and air conditioning equipment generally require that refrigerant be recovered by a certified technician, with documentation confirming who performed the recovery and when. This applies whether the refrigerant recovery is performed as part of the removal scope or coordinated separately with a certified provider — depending on project conditions, additional local or facility-specific requirements may also apply.
Practically, this means refrigerant recovery has to be scheduled and completed before mechanical disconnection and rigging begin — it can’t be an afterthought once the unit is already partially disassembled. On multi-unit removal projects, we coordinate the recovery sequence so refrigerant work doesn’t become a bottleneck holding up the rest of the schedule.
How Does the Removal Process Actually Work?
A typical CRAC or CRAH removal project moves through a consistent sequence, though the specific order and duration depend on the unit count, facility conditions and whether the space needs to stay operational during the work:
1. Site walk and equipment inventory — confirming manufacturer, model, cooling type (DX versus chilled water), capacity and physical access conditions for each unit.
2. Shutdown and isolation coordination — working with facility engineering or building management to de-energize electrical circuits and isolate piping without affecting adjacent systems still in service.
3. Refrigerant recovery (DX units) or chilled-water/glycol drain-down (CRAH units), performed and documented as required.
4. Electrical and piping disconnection, including tracing dedicated circuits, disconnecting condensate lines, and separating supply/return piping at appropriate isolation points.
5. Rigging and extraction, which may involve disassembling the cabinet into sections, routing through doorways or freight elevators, or using floor openings where raised-floor access allows.
6. Loadout and transportation to a recycling, resale or disposal destination depending on the unit’s condition and market value.
7. Site cleanup and floor/wall patching at the former unit location as part of turnover requirements.
Access is often the deciding factor in how long a project takes. A unit sitting in an open mechanical room is a very different job than one wedged into a data hall between active racks, or installed on a mezzanine with limited overhead clearance.
Is There Value in the Equipment Before It’s Scrapped?
Not every retired CRAC or CRAH unit is scrap-only. Depending on age, condition, completeness and current demand in the secondary equipment market, some units — or usable components such as compressors, coils, blower assemblies and control boards — may have resale or reuse value. Copper, aluminum and steel content also carries recyclable commodity value even when a unit isn’t a candidate for resale.
We evaluate this as part of scope development rather than assuming every unit goes straight to demolition. Recoverable value from resalable equipment or scrap material can help offset a portion of the overall removal cost, though it isn’t guaranteed on every project and depends heavily on the specific equipment involved.
What Should I Have Ready Before Requesting a Quote?

Facility managers get the most useful evaluation from our team when they can provide a few basic details up front:
- Manufacturer and model number for each unit (a photo of the nameplate works well)
- Cooling type — DX/air-cooled, DX/water-cooled, or chilled water
- Approximate tonnage or capacity if known
- Number of units and their locations within the facility
- Whether the space needs to remain operational during removal, or is already shut down
- Access conditions — floor level, doorway widths, freight elevator availability, raised floor or slab
- Target timeline, including any lease-turnover or shutdown deadlines
Quick Pre-Project Checklist
Before crews mobilize, it helps to confirm:
- ☐ Electrical circuits serving the unit(s) have been identified and can be safely de-energized
- ☐ Refrigerant type and estimated charge are known, or can be confirmed on-site
- ☐ Chilled-water or condensate piping isolation valves are identified and accessible
- ☐ Rigging path from the unit to the building exterior or loading dock has been walked
- ☐ Any adjacent equipment that must remain operational has been flagged
- ☐ Building management or landlord approvals for after-hours or weekend work are in place, if needed
Serving Fresno and the Broader Central Valley
USA Decom provides CRAC and CRAH removal services for facilities throughout Fresno and the surrounding Central Valley, including Clovis, Madera, Visalia, Hanford, Merced and communities along the Highway 99 corridor, as well as facilities in the broader San Joaquin Valley extending toward Bakersfield and Modesto. Whether the project involves a single server room in a distribution facility or a multi-unit data hall retirement, the disconnection, rigging and disposition considerations are largely the same — only the scale changes.
Tell Us About Your Project
If you’re planning a CRAC or CRAH removal in Fresno or anywhere in the Central Valley, use the form below to tell our team about the facility, the equipment involved and your timeline. Include manufacturer and model information where you have it, the number of units, whether the space needs to stay operational, and any lease or shutdown deadlines driving the schedule. That information lets us put together an accurate scope and next steps for your project.