A cooling tower rarely gets replaced or removed in isolation. By the time a Los Angeles facility manager starts researching cooling tower removal, there’s usually a chiller plant upgrade underway, a rooftop mechanical yard being cleared for redevelopment, an old counterflow unit that’s been leaking basin water into a parking structure below, or a building owner preparing a property for a new tenant with different HVAC requirements. Whatever the trigger, the tower still has to come down, and that work involves more than unbolting a fan deck.
USA Decom removes open-circuit and closed-circuit cooling towers from commercial, industrial, institutional and mixed-use properties throughout Los Angeles and the surrounding metro. This page walks through the questions we’re typically asked before a facility manager, property engineer or general contractor requests a quote, along with the practical considerations that shape scope, schedule and cost.
What Does Cooling Tower Removal Actually Involve?
A complete cooling tower removal generally covers more equipment than the visible tower structure itself. Depending on the installation, scope can include:
- Fan assemblies, motors and gear-reducers (or gearboxes) at the fan deck
- Fill media, drift eliminators and louvers
If you have a project coming up, use the form below to tell our team about the facility, equipment and schedule.
- Cold-water basins, including any integral steel basin pans
- Distribution piping, spray nozzles and internal water headers
- Condenser-water supply and return piping connections outside the tower footprint
- Structural steel casing, support framing, platforms, ladders and access stairs
- Controls, VFDs, level switches and associated electrical connections
On a factory-assembled unit sitting on a rooftop curb, most of this comes off as a coordinated dismantling sequence. On a larger field-erected, multi-cell installation, the same categories of equipment exist but are spread across a much larger structural footprint, often requiring section-by-section disassembly rather than a single lift.
Before mobilizing, we typically need to understand whether the tower is being fully removed and the roof or pad restored, or whether it’s being replaced in place with a similar footprint. That distinction changes how piping is capped, whether the structural curb or foundation stays in place, and what the final condition of the mechanical area needs to look like at turnover.
Why Los Angeles Presents Its Own Set of Removal Conditions
Cooling tower removal in Los Angeles isn’t the same project as removal in a market with more ground-level industrial space. A large share of the region’s cooling towers sit on rooftops — office towers in Downtown LA and Century City, hospitals and medical campuses, hotels, studio and production facilities, and mixed-use buildings across the Westside and San Fernando Valley all commonly run rooftop mechanical yards rather than ground-mounted plants.
That rooftop concentration drives several practical realities:
- Crane access is constrained. Downtown high-rises, Mid-Wilshire buildings and dense Westside properties often have limited street frontage, tight loading zones and permitted crane windows that may require early-morning or weekend lifts.
- Roof loading and access paths matter. Even a tower being cut apart for piece-small removal still generates concentrated point loads at staging areas, and elevator or hoistway dimensions frequently limit how large a section can travel down through the building instead of over the parapet.
- Seismic bracing is common on West Coast installations. Towers manufactured for California markets are frequently specified with additional structural bracing to meet regional wind and seismic requirements, which affects how the casing and support steel are sequenced for disassembly.
- Active buildings stay active. Hospitals, hotels, studios and occupied office towers usually need the mechanical plant to keep running until the new equipment is ready, which means removal has to be phased around live systems rather than a simple shutdown-and-clear approach.
Beyond the immediate Los Angeles core, we also see this same mix of rooftop and industrial-park cooling tower installations across the broader region — Burbank and Glendale’s media and production facilities, the industrial corridors around Vernon, Commerce and the City of Industry, the South Bay’s aerospace and logistics facilities, and inland markets including the San Gabriel Valley, Long Beach, Pasadena and Orange County’s northern cities. USA Decom provides cooling tower removal services across these markets as well.
Do You Need a Crane, or Can the Tower Be Dismantled in Place?

This is usually the first technical question we work through with a facility manager, because it drives both schedule and cost.
Rooftop, factory-assembled towers are frequently disassembled into manageable sections — fan decks, casing panels, fill sections and basin components — that can be rigged down through a roof hatch, freight elevator or, when access allows, lowered by crane to a ground-level container. Smaller single-cell units in the 100- to 250-ton range often come apart faster because the casing sections and mechanical components are lighter and more modular.
Field-erected and multi-cell towers, common at industrial plants, larger commercial campuses and some hospital central plants, are typically dismantled through a more structured sequence: fans and drive systems first, then fill media and eliminators, then the structural casing and internal partition walls, and finally the basin and support steel. A field-erected tower in the 500- to 1,500-ton-plus range may involve multiple cells that each need to be sequenced independently, particularly if the plant needs partial cooling capacity to remain online during removal.
Either way, before quoting a project we typically want to know:
- Rooftop, grade-level or elevated structural platform installation
- Whether the tower is single-cell or multi-cell
- Whether a crane pick is feasible, or whether the unit must be manually rigged and lowered
- Building access constraints — freight elevator dimensions, roof hatch size, loading dock hours
- Whether the plant needs to remain partially operational during removal
What Types and Brands of Cooling Towers Does USA Decom Remove?
We remove open-circuit and closed-circuit (fluid cooler) systems in both crossflow and counterflow configurations, whether the unit is factory-assembled or field-erected. Commonly encountered equipment includes:
- SPX Cooling Technologies / Marley — including the Marley NC and NC Everest crossflow series and the MD and MD Everest counterflow series. The NC Everest is a crossflow evaporative-cooling system designed to deliver more cooling capacity per unit footprint than earlier single-cell, factory-assembled towers, and the MD Everest counterflow tower is delivered to the job site in factory-assembled modules, with a structure built to meet seismic and wind load requirements under applicable building codes — a detail that’s directly relevant to how these units are braced and disassembled in California installations.
- Baltimore Aircoil (BAC) — including Series 3000 and Series 1500 crossflow towers. The Series 3000 uses a crossflow design with large access doors and an internal walkway option, providing access to the cold water basin, hot water basin and drive system, with factory-assembled platforms and ladders on many configurations — features that also affect how quickly a removal crew can gain internal access during dismantling.
- EVAPCO — including AT-series and UT/UAT induced-draft, factory-assembled towers commonly found on both commercial rooftops and industrial plant sites.
- Legacy and secondary brands including Recold, Ceramic Cooling Tower, Tower Tech and Delta Cooling Towers, which still show up on older installations throughout the region.
Recognizing the manufacturer and model on the nameplate helps our team anticipate how the unit was assembled — and, just as important, how it comes apart safely and efficiently.
How Does Tower Size Change the Removal Approach?
Tonnage and cell count drive nearly every decision on a cooling tower removal project:
- Small rooftop units (100–250 tons): Often a single crew can dismantle and rig these down within a compressed schedule, especially when roof access allows a small crane or manlift.
- Mid-size commercial towers (250–750 tons): These frequently involve two or more cells or a heavier structural casing, requiring more sequencing between fan removal, fill removal and structural disassembly.
- Large industrial and field-erected towers (1,000–1,500+ tons): Multi-cell, field-erected systems require the most structured approach — isolating individual cells, coordinating with plant operations if partial capacity needs to stay online, and managing a larger volume of structural steel, piping and mechanical components.
Larger installations also generate meaningfully more recoverable material — more structural steel, more copper and aluminum in motors and controls, and more mechanical components with potential secondary-market value — which factors into the overall project economics.
What Happens to the Piping, Basins and Structural Steel?
Once the mechanical components — fans, motors, gear-reducers, fill and eliminators — are removed, the remaining scope typically centers on three areas:
Piping. Condenser-water supply and return lines are disconnected at the tower connection points. Depending on whether the tower is being replaced or the plant is being fully decommissioned, piping may be capped, partially removed, or fully demolished back to a specified point.
Basins. Cold-water basins are drained, cleaned and removed. Integral steel basins on factory-assembled towers typically come out with the rest of the casing; concrete basins on field-erected installations require separate demolition and disposal.
Structural steel and platforms. Casing panels, internal partitions, access platforms, ladders and support framing are dismantled and staged for loadout. On rooftop projects, this often means breaking material down to sizes that fit through existing access paths rather than lifting large assembled sections.
The end condition matters as much as the removal itself. A tower coming out ahead of a chiller plant retrofit may only need the footprint cleared and utilities capped, while a full facility turnover may require the roof curb, structural supports and any penetrations restored to a condition specified by the property owner or general contractor.
Is There Recoverable Value in a Decommissioned Cooling Tower?

Cooling towers contain a fair amount of recoverable material. Motors, gear-reducers, drive shafts, VFDs and controls may have resale or reuse value depending on age, condition and remaining service life. Structural steel, along with copper and aluminum content in electrical and mechanical components, typically has scrap value. Fill media and PVC components generally do not carry meaningful resale value and are usually recycled or disposed of according to applicable requirements.
We evaluate recoverable equipment and material as part of project planning rather than sending everything to the scrap yard by default. Recovered value doesn’t offset every project’s removal cost, but on a larger multi-cell tower with functional motors, drives and steel, it can meaningfully affect the overall economics of the job.
Projects in Action
Rooftop cooling tower removals in dense buildings like those found throughout Los Angeles tend to follow a similar sequence in our experience: a pre-removal site walk to confirm access paths and crane feasibility, coordination with building management on freight elevator scheduling and rooftop access windows, isolation of the tower from the condenser-water loop, then a staged dismantling — fans and drives first, followed by fill and casing sections, then basin and structural steel — with material broken down to sizes that clear the building’s access constraints. On larger industrial and field-erected towers, our experience with similar work typically involves sequencing cell-by-cell removal so a plant can maintain partial cooling capacity if needed, followed by structural disassembly and site restoration once the mechanical components are cleared.
Cooling Tower Removal Checklist: What to Have Ready Before You Request a Quote
Having the following information ready helps us evaluate your project faster:
- Manufacturer and model (if known), or at least tonnage and configuration
- Whether the tower is rooftop, grade-level or on a structural platform
- Single-cell or multi-cell, factory-assembled or field-erected
- Whether the tower is being fully removed or replaced in place
- Site access details — crane feasibility, freight elevator size, loading dock hours
- Whether the plant needs to remain partially operational during the project
- Target schedule, including any lease, shutdown or construction deadlines
- Photographs of the tower, mechanical yard and access route, if available
Tell Us About Your Cooling Tower Project
Whether you’re clearing rooftop mechanical space for a chiller plant upgrade, decommissioning a field-erected tower at an industrial site, or preparing a Los Angeles property for redevelopment or tenant turnover, use the form below to tell our team about the facility, the tower’s size and manufacturer if known, access conditions and your target schedule. That information lets us put together a removal plan suited to your specific building and project timeline.